The Energy Control Program and Who Does What
Module 2 · Program, People, and Devices

The Energy Control Program and Who Does What

Learn the three pillars of an OSHA energy control program (written procedures, training, and periodic inspections), what a machine-specific procedure must contain, and the difference between authorized, affected, and other employees.

Three Pillars

OSHA 1910.147 requires an energy control program with three parts:

  1. 1 Procedures

    Written, machine-specific steps

  2. 2 Training

    By role; retrain when things change

  3. 3 Periodic inspection

    At least annually; certified

Inspection findings drive updates to procedures and retraining.

A binder of procedures nobody follows is not a program. All three pillars have to work together.


Who Does What: The Three Roles

RoleWhoWhat they must know
Authorized employeeThe person who locks or tags out equipment to service itRecognize hazardous energy sources, the type and magnitude of energy, and the methods to isolate and control it
Affected employeeSomeone who operates or uses the equipment, or works in the area where servicing happensThe purpose and use of energy control procedures; never try to restart locked or tagged equipment
Other employeeAnyone whose work may be in an area where LOTO is usedThe procedure exists, and they must not remove locks or restart equipment

An affected employee becomes an authorized employee when they perform servicing that requires LOTO. They need that training first.


Machine-Specific Procedures

General “how to lock out” instructions aren’t enough for most equipment. OSHA requires documented procedures that clearly spell out, for the equipment involved:

  1. The intended use of the procedure (which machine, which tasks)
  2. Steps for shutting down, isolating, blocking, and securing the machine
  3. Steps for placing, removing, and transferring lockout/tagout devices, and who is responsible
  4. Requirements for testing the machine to verify the effectiveness of the lockout

What Good Procedures Look Like

Most plants use one-page visual procedures posted at the machine:

  • Photos of each isolation point, numbered
  • Energy type and magnitude (e.g., “480 VAC,” “90 psi air,” “2,000 psi hydraulic accumulator”)
  • Device location and the method (e.g., “Turn handle OFF, apply lock”)
  • Stored energy steps (bleed, block, discharge)
  • Verification method for each source
  • Release steps

When Documentation Isn’t Required

OSHA’s standard includes a narrow exception: a written procedure isn’t needed for a specific machine if all of a list of conditions are met. These include that the machine has no potential for stored or residual energy after shutdown, has a single energy source that can be readily identified and isolated, isolation fully de-energizes it, it’s locked by a single lockout device under the exclusive control of the authorized employee, and there have been no prior accidents involving unexpected activation during servicing. If any condition isn’t met, write the procedure. Most industrial machines don’t qualify.


Training

WhenRequirement
InitialBefore an employee performs or is affected by LOTO, appropriate to their role
RetrainingWhen job assignments change, machines or processes change and create new hazards, procedures change, or a periodic inspection (or other reason) shows deviations or gaps in knowledge
DocumentationThe employer must certify that training was done, with names and dates

If your plant uses tags only for some equipment, training must also cover the limitations of tags (Lesson 2.2).

⚠️ Common Pitfall: The Procedure Written in the Office

Common mistake: procedures are written from drawings by someone who never walked the machine.

The result: a missed second disconnect, a valve that’s actually behind the machine, an accumulator nobody listed. Write and validate every procedure at the machine, with the people who service it, and test it by actually performing the lockout.


Key Takeaway

An energy control program has procedures, training, and periodic inspections. Authorized employees apply locks; affected employees operate the equipment and must never restart it while locked out; other employees must leave it alone. Procedures must cover shutdown, isolation, device placement and removal, stored energy, and verification, and should be visual and validated at the machine.

🧪 Try It: Assign the Roles

Classify each person during a gearbox replacement on a palletizer:

  1. The millwright who locks out the palletizer and removes the gearbox. (Authorized.)
  2. The palletizer operator who is told the machine is down. (Affected.)
  3. A forklift driver who passes through the area. (Other.)
  4. The operator who later helps lock out to adjust a sensor. (Becomes authorized. Must be trained as authorized first.)
🧠 Knowledge Check

1. What are the three main parts of an energy control program?

2. Who applies lockout devices to service a machine?

3. Which of these must a machine-specific procedure include?

4. When must retraining occur?