Testing, Positioning, and Alternative Measures
Module 4 · Complex Lockouts

Testing, Positioning, and Alternative Measures

Learn the OSHA sequence for temporarily removing locks to test or position a machine, how to design effective alternative measures for routine minor servicing, and how energized troubleshooting is handled under electrical safety rules.

When You Need Energy Back, Briefly

Some jobs require power partway through: jogging a conveyor to line up a splice, bumping a motor to check rotation, or running a machine to test a repair. OSHA allows lockout devices to be temporarily removed for testing or positioning, but only in a specific sequence.

  1. 1 Clear tools

    Remove tools and materials

  2. 2 Clear people

    Everyone out of the machine area

  3. 3 Remove locks

    Using the release procedure

  4. 4 Energize

    Test or position

  5. 5 Re-lock

    De-energize; full lockout again

Before servicing resumes, the full lockout sequence, including verification, is repeated.

Key points:

  • Treat the removal exactly like a full release (Lesson 5.1): inspect, notify, and account for everyone.
  • When you’re done testing, the machine goes back to a fully locked and verified state before anyone goes back in.
  • No one works inside the danger zone while energy is restored.
⚠️ Common Pitfall: Jogging While Someone Holds the Belt

Common mistake: a mechanic stays inside to guide a belt while a coworker jogs the motor “just a bump.”

That’s servicing in the danger zone with energy restored, which is exactly what LOTO is meant to prevent. If positioning needs a hand inside, use a method that keeps hands out (hand-turning with locks on, a barring device, or a dedicated, safeguarded inching mode designed for this purpose under a documented procedure).


Alternative Measures for Minor Servicing

Recall the minor servicing exception: routine, repetitive tasks integral to production don’t require LOTO if effective alternative measures protect the worker. Examples of well-designed alternatives:

TaskAlternative measure
Clearing a jam at a guarded infeedInterlocked guard monitored by a safety-rated system that stops hazardous motion and prevents restart while open
Adding labels to a running labelerTool or access port that keeps hands outside the danger zone
Wiping a sensor lensSensor relocated or a cleaning port added outside the guard
Clearing a film wrap at a stretch wrapperSafety-rated stop plus a trapped-key system for guard entry

What makes them effective:

  • Designed using risk assessment and machine safety standards (such as ANSI B11 and ISO 13849 for safety-rated controls)
  • Protect against all hazards for that task, including stored energy
  • Documented, with training, so the task is done the same way every time

If a task falls outside the defined alternative measure (a bigger jam, a different access point, a broken interlock), go back to full lockout.


Energized Electrical Troubleshooting

Diagnosing electrical faults sometimes requires taking voltage measurements on live circuits. That isn’t lockout; it’s energized work, governed by electrical safe work practices such as OSHA 1910.333 and NFPA 70E. In general:

  • Only qualified persons do it.
  • Work on energized parts must be justified. De-energizing is the default.
  • The hazards (shock and arc flash) are assessed, and appropriate PPE, tools, and boundaries are used.
  • Many sites require an energized electrical work permit for anything beyond diagnostic testing.

Once troubleshooting finds the problem, the repair is done under lockout.


Key Takeaway

You may temporarily remove locks to test or position only by following the sequence: clear tools, clear people, remove locks per release, energize, then fully re-lock before resuming. Minor servicing alternatives must be engineered, documented, and effective against all hazards. Live electrical troubleshooting is energized work under electrical safety rules, and repairs happen under lockout.

🧪 Try It: Test or Not?

After replacing a motor, the electrician needs to check rotation direction. Write the steps they should follow.

Clear all tools from the drive. Make sure everyone is out of the machine area. Notify affected employees. Remove locks using the release procedure. Bump the motor and observe rotation from a safe position. De-energize, re-apply all locks, release stored energy, and verify before correcting the rotation (swapping leads) under lockout.

🧠 Knowledge Check

1. What must happen before locks are removed to test a machine?

2. After testing or positioning, what must happen before servicing resumes?

3. Which is an example of an effective alternative measure for routine jam clearing?

4. Live voltage measurements during troubleshooting are governed by: