Releasing from Lockout and Restoring Energy
Module 5 · Release and Inspection

Releasing from Lockout and Restoring Energy

Follow the required steps to safely restore equipment to service, including inspecting the machine, accounting for every person, notifying affected employees, and removing your own lock, plus the strict procedure for removing an absent worker's lock.

Restart Is a Hazard Too

The job is done, everyone’s ready to run, and production is waiting. That pressure is exactly when people get hurt: a guard left off, a wrench left on a shaft, a coworker still inside the machine.

OSHA requires a specific release procedure before locks come off.

  1. 1 Inspect machine

    Tools out; parts intact

  2. 2 Guards on

    Reinstall and secure

  3. 3 Account for people

    Everyone clear and safe

  4. 4 Notify

    Tell affected employees

  5. 5 Remove own lock

    Only the person who applied it

  6. 6 Restore energy

    In a safe order


Step by Step

1. Inspect the Machine

  • Remove nonessential items: tools, rags, parts, blocks, and shims.
  • Make sure components are operationally intact, meaning bolts tight, belts on, couplings connected.
  • Reinstall and secure guards and safety devices.
  • Remove blocks and pins used for stored energy, in the correct order (only after it’s safe to let the load be supported by the system again).

2. Account for Everyone

  • Check that all employees are safely positioned or removed from the machine area.
  • Use the group lockbox sign-in board or a headcount.
  • Physically look inside enclosures, pits, and behind the machine.

3. Notify Affected Employees

After locks are removed and before the machine starts, affected employees must be told that the lockout devices have been removed.

4. Remove Your Own Lock

Each lockout or tagout device must be removed by the authorized employee who applied it. Nobody else removes your lock, and you never remove anyone else’s.

5. Restore Energy Safely

  • Return controls to OFF before restoring power (they should already be, from verification).
  • Restore energy in a safe order. For example, restore air with a soft-start, and know whether any double-solenoid valves will move cylinders when air returns.
  • Stand clear and watch the first cycle.

When the Person Who Applied the Lock Is Gone

Sometimes a lock is left on and its owner has gone home, is on vacation, or has left the company. OSHA allows removal by someone else only under the employer’s direction, using a specific documented procedure with specific training. At a minimum, the procedure must include:

  1. Verification by the employer that the authorized employee who applied the device is not at the facility
  2. All reasonable efforts to contact that employee to tell them their lock is being removed
  3. Making sure the employee knows the lock was removed before they resume work at the facility

Most plants add more: a supervisor and a second authorized person inspect the machine together, confirm no one is inside, and document every step.

⚠️ Common Pitfall: Bolt Cutters Without the Procedure

Common mistake: a supervisor cuts a lock because “they must have forgotten it and gone home.”

What if they didn’t go home? What if they’re inside the machine, or on a break and about to go back in? Locks are cut only after the full procedure is followed, starting with confirming the person is not at the facility. A forgotten lock costs some production time. A wrong assumption can cost a life.


Key Takeaway

Before release: inspect the machine, reinstall guards, remove blocks, account for everyone, and notify affected employees. Each person removes only their own lock. An absent worker’s lock comes off only through the documented procedure: confirm they’re not at the facility, make reasonable efforts to contact them, and inform them before they return.

🧪 Try It: Release Checklist

Write a one-page release checklist for a machine you know. Include:

  • Tools, rags, and parts removed (list common items left behind on this machine)
  • Guards and covers reinstalled (list each by location)
  • Blocks and pins removed (list each)
  • Everyone accounted for (how?)
  • Affected employees notified (who?)
  • Each person removes their own lock
  • Energy restored in order (list the order)
  • First cycle observed from a safe position
🧠 Knowledge Check

1. Who may remove a lockout device under normal conditions?

2. When must affected employees be notified during release?

3. Which is required before removing an absent employee's lock?

4. What should be done with blocks and pins used to restrain stored energy before restart?