The Lockout Sequence, Step by Step
Module 3 · Applying Lockout

The Lockout Sequence, Step by Step

Walk through the required order of lockout (prepare, notify, shut down, isolate, apply devices, control stored energy, and verify) with what to do and what goes wrong at each step.

The Order Matters

OSHA 1910.147 lays out the application of energy control in a specific sequence. Doing the steps out of order creates gaps. For example, isolating before a normal shutdown can damage equipment or release energy violently.

  1. 1 Prepare

    Review procedure; know every energy source

  2. 2 Notify

    Tell affected employees

  3. 3 Shut down

    Normal stop

  4. 4 Isolate

    Every source, at the device

  5. 5 Lock + tag

    Your own lock on each point

  6. 6 Stored energy

    Bleed, block, discharge

  7. 7 Verify

    Try to start; test for zero

If verification shows any energy remaining, stop: find the missed source, isolate it, and verify again.

1. Prepare

Before touching anything, the authorized employee must know:

  • The type and magnitude of every energy source
  • The hazards of that energy
  • The methods to control it

Get the machine-specific procedure. Gather the right locks, tags, devices, test equipment, and blocks. If the job scope changed (for example, now you need to open a hydraulic line), make sure the procedure covers it.

2. Notify Affected Employees

Tell the operators and others in the area that the machine is being locked out, and why. This prevents surprises, like an operator trying to “help” by restarting.

3. Shut Down

Stop the machine using its normal stopping procedure: the stop button, the cycle-stop, or the control system. A normal stop brings moving parts to rest in a controlled way and avoids damage or added hazards from cutting power to a running machine.

4. Isolate

Operate every energy-isolating device so the machine is isolated from all sources: electrical disconnects, air valves, hydraulic valves, steam, process lines, and so on.

  • Isolate at the device, not at controls.
  • Watch for machines fed from more than one electrical source (main power, a separate control transformer feed, a UPS, heater circuits).

5. Apply Lockout/Tagout Devices

Each authorized employee applies their own lock (and tag, where used) to each isolating device:

  • Lock holds the device in the safe or OFF position.
  • Tag is attached at the same point, stating who, when, and why.
  • Use hasps or group lockboxes when several people work on the job (Module 4).

6. Control Stored Energy

After isolation, release, restrain, or otherwise make safe all stored and residual energy:

  • Bleed air and hydraulic pressure; drain or block accumulators
  • Discharge capacitors (and wait for drives to discharge)
  • Block or lower raised parts; install safety pins
  • Release or block spring tension
  • Let flywheels and rolls coast to a full stop
  • Cool hot surfaces or allow time; vent and drain process lines

If stored energy could re-accumulate (for example, pressure building again), keep checking it until the job is done.

7. Verify Isolation

Before starting work, verify the machine is isolated and de-energized:

  1. Make sure everyone is clear of the machine.
  2. Try to start it with the normal controls (the “try-out”).
  3. Test electrical circuits for absence of voltage with a properly rated meter.
  4. Check gauges read zero for air and hydraulics.
  5. Return the controls to OFF or neutral after the try-out.
⚠️ Common Pitfall: Leaving the Start Button On After Try-Out

Common mistake: the tech presses Start during verification, nothing happens (good), and they go to work. The start selector is left in RUN.

When the locks come off later, the machine starts instantly, possibly while someone is still reaching in. Always return controls to OFF or neutral after the try-out.


Key Takeaway

Follow the sequence: prepare → notify → shut down → isolate → lock and tag → control stored energy → verify. Isolate every source at the device, put your own lock on each, release or block stored energy, and try to start and test before work begins. Return controls to OFF after trying.

🧪 Try It: Put the Steps in Order

A mechanic is about to change a cutting blade on a carton sealer. Put these in the correct order:

  • A. Press Start to confirm nothing moves, then return the switch to OFF
  • B. Tell the operator the machine is going down
  • C. Bleed air at the dump valve and pin the raised sealing head
  • D. Read the machine-specific procedure
  • E. Apply a personal lock to the disconnect and the air dump valve
  • F. Stop the machine with the cycle-stop button
  • G. Turn the disconnect OFF and close the air dump valve

Answer: D, B, F, G, E, C, A

🧠 Knowledge Check

1. Which step comes immediately before isolating energy sources?

2. Why should you stop the machine normally before opening the disconnect?

3. What should you do after pressing Start during verification and confirming nothing moves?

4. If stored energy could build back up during the job, what must you do?