The Full Lifecycle

  1. M3 Prepare + notify

    Procedure, energy sources, people

  2. M3 Shut down + isolate

    Normal stop; every source

  3. M2 Lock + tag

    One person, one lock, one key

  4. M3 Stored energy

    Bleed, block, discharge

  5. M3 Verify

    Try-out; live-dead-live

  6. M5 Release

    Inspect, account, notify, own lock

  7. M5 Inspect program

    At least annually

Annual periodic inspections and changes to equipment feed back into better procedures and training.

Glossary

TermMeaning
Affected employeeOperates or uses equipment being serviced, or works in the area
Alternative measuresEffective protection that allows minor servicing without LOTO
Authorized employeeLocks or tags out equipment to service it
Double block and bleedTwo closed valves with a vent between, for process line isolation
Energy-isolating devicePhysical device that prevents energy transmission (disconnect, valve, block, blind)
Full employee protectionTagout protection equivalent to lockout, using extra measures
Group lockboxBox holding isolation keys, locked by every worker on a job
HaspDevice that lets multiple locks be applied to one point
Live-dead-liveTest the tester, test the circuit, test the tester again
Lockout deviceLock that holds an isolating device in the safe position
Minor servicingRoutine, repetitive, integral tasks; exempt only with effective alternative measures
Other employeeWorks where LOTO may occur; must not remove locks or restart
Periodic inspectionAnnual check of each procedure by another authorized employee
Primary authorized employeeCoordinator responsible for a group lockout
Stored (residual) energyEnergy remaining after isolation: capacitors, springs, pressure, gravity
Tagout deviceWarning tag; doesn’t physically prevent operation
Try-outAttempting to start the machine to verify isolation
Zero energy stateEvery energy source isolated, stored energy released, and verified

Key Requirements at a Glance

TopicRequirement
StandardOSHA 29 CFR 1910.147
Program partsProcedures, training, periodic inspections
DevicesProvided, singularly identified, durable, standardized, substantial, identifiable
Tag attachmentsNon-reusable, self-locking, at least 50 lb unlocking strength
SequencePrepare, shut down, isolate, apply devices, stored energy, verify
ReleaseInspect, account for people, notify, remove own lock
Absent worker’s lockVerify not at facility, reasonable contact efforts, inform before return
Periodic inspectionAt least annually, by another authorized employee, certified

🧪 Try It: Capstone: Write a Machine-Specific Procedure

Choose a machine with at least three energy sources. Write a one-page visual procedure with:

  1. Machine name, location, and the tasks it covers
  2. A table of each energy source, its magnitude, its isolating device, and its location (add a photo for each)
  3. Shutdown steps
  4. Isolation and lock steps for each device
  5. Stored energy steps for each source
  6. Verification steps (try-out, gauges, voltage test)
  7. Release steps
  8. Who wrote it, who validated it at the machine, and the date

Then have an authorized coworker perform it while you observe, and fix what you learn.

🧠 Knowledge Check

1. What is the correct order of these lockout steps?

2. An operator presses Start on a machine with a lock on its disconnect, but the operator didn't apply that lock. What role are they in?

3. Which is NOT an energy-isolating device?

4. A hydraulic system is isolated and the pump gauge reads zero. Before opening a line, what else must you check?

5. During a shift change on a group lockout, what's the safe sequence?

6. Who must perform the annual periodic inspection of a procedure?