Lift Planning and Critical Lifts
Plan routine and critical lifts step by step: weights, radius, capacity, rigging, ground and wharf conditions, wind, exclusion zones, pre-lift meetings, test lifts, and why no one stands under a suspended load.
Every Lift Is Planned
Routine container moves are planned by the terminal’s procedures and TOS. Non-routine lifts (breakbulk, project cargo, equipment, maintenance) need a lift plan. The more unusual or heavy the lift, the more detailed the plan.
- 1 Load
Weight, CG, lift points
- 2 Crane
Configuration, radius, chart
- 3 Rigging
Sized for worst leg; inspected
- 4 Site
Wharf/ground, obstacles, wind
- 5 Zone + meeting
Barricade; roles; signals
- 6 Test lift
A few inches; check
- 7 Lift
Smooth, controlled, tag lines
What Makes a Lift “Critical”?
Definitions vary by company, but a lift is often designated critical when it involves:
- A load above a set percentage of the crane’s chart capacity (commonly in the 75–90% range, per company rules)
- Two or more cranes lifting one load (tandem lift)
- Lifting personnel
- Lifts over occupied areas, operating equipment, or live process lines
- Unusual or high-value loads, or loads with uncertain weight or CG
- Lifts near power lines
Critical lifts typically require a written, engineered plan, review and sign-off by qualified persons, and a documented pre-lift meeting.
The Lift Plan
A written lift plan usually includes:
| Item | Details |
|---|---|
| Load | Weight (verified), dimensions, CG, lifting points |
| Crane | Make, model, configuration, counterweight, outriggers or position |
| Radii | Pick, swing, and set radii; chart capacity at the worst radius |
| Rigging | Each component’s WLL, weight, and calculated load (sling angles) |
| Total load and percent of capacity | Load + rigging ÷ chart capacity |
| Ground / wharf | Bearing capacity, mats, deck load limits on ships |
| Environment | Wind limits, visibility, tide and vessel movement, lighting |
| Hazards | Power lines, structures, other cranes, traffic |
| Exclusion zone | Barricades and spotters |
| People | Operator, signal person, riggers, lift director |
| Communication | Signals and radio channel |
| Contingencies | What to do if wind rises or the load shifts |
Lifting On and Off Ships
Ship lifts have special challenges:
- The ship moves. Tide, wind, swell, and passing traffic make the vessel rise, fall, and surge. Landing a load on a moving deck takes coordination.
- Ship stability. Heavy lifts shift the vessel’s weight and can cause it to list. The ship’s officers must agree to the lift and manage ballast.
- Deck strength. Decks and hatch covers have load limits. Use dunnage to spread loads.
- Ship’s gear. If the ship’s own cranes are used, they must be certified and in good condition.
The Exclusion Zone
- Barricade the area under and around the load path.
- Never stand or walk under a suspended load.
- Keep people out of pinch points between the load and fixed objects.
- Keep clear of the crane’s swing radius (counterweight) on mobile and harbor cranes.
The Test Lift
Lift the load a few inches off its supports and hold:
- Is the load level (hook over CG)?
- Are slings seated and hardware aligned?
- Do the brakes hold?
- Does the RCI read as expected?
If anything is off, set it down and fix it.
Common mistake: a large, flat piece of cargo (like a panel or a ship’s hatch cover) is lifted on a day that’s within the crane’s general wind limit.
Large surface areas act like sails. The load spins, swings, or pulls the crane beyond its rating even in moderate wind. Lift plans for high-sail-area loads need load-specific wind limits and extra tag line control.
Key Takeaway
Plan every non-routine lift: load, crane, radius, rigging, site, wind, zone, people, communication. Designate critical lifts by percentage of capacity, tandem, personnel, or hazard, with written plans and sign-off. Ship lifts involve vessel motion, stability, and deck limits. Barricade, never stand under a suspended load, and always make a test lift.
Your company’s rule: a lift is critical above 80% of chart capacity, or for tandem lifts, personnel, or lifts over operating equipment.
- A 40-ton breakbulk lift at 72% capacity, onto a clear wharf. (Not critical by percentage. Still needs a standard lift plan.)
- A 25-ton lift at 55% capacity, swinging over an operating conveyor. (Critical, because it’s over operating equipment.)
- Two mobile harbor cranes lifting one 120-ton module together. (Critical: tandem lift.)
- A 30-ton lift at 84% capacity. (Critical by percentage.)
1. Which of these commonly makes a lift 'critical'?
Tandem lifts, high percent of capacity, personnel lifts, and lifts over hazards are typically critical.
2. What should happen during a test lift?
A short test lift reveals rigging, balance, and brake problems before full commitment.
3. Why must the ship's officers agree to a heavy lift on or off the vessel?
Heavy lifts change weight distribution and can cause list. Officers manage ballast and stability.
4. Where should workers never be during a lift?
Never stand under a suspended load.